Files
roadmap/content/qa/nomos/2025q1-da-testing.md
2025-11-10 14:57:56 +02:00

3.0 KiB
Raw Blame History

title, tags, draft, description
title tags draft description
Nomos Data Availability Testing
2025q1
qa
nomos
false Implement data availability test plans for the Nomos project at the cluster level.

vac:qa:nomos:2025q1-da-testing

Description

Implement data availability test plans for the Nomos project at the cluster level.

Alignment with VAC Narratives:

  • By developing and constantly updating tests for data availability, VAC QA ensures that the feature's implementation aligns with high standards.
  • This continuous testing helps identify any spec-related issues early, contributing to the RFC culture and improving spec quality.
  • The effort also supports IFT's strategic objective of scaling the projects capacity and ensuring a reliable system for future community involvement.

Task List

Data Integrity Tests

  • fully qualified name: vac:qa:nomos:2025q1-da-testing:data-integrity-tests
  • owner: romanzac
  • status: done
  • start-date: 2025/01/06
  • end-date: 2025/01/17

Description

Add integration tests focusing on the system's ability to reconstruct or retrieve data.

Deliverables

Networking and Privacy Tests

  • fully qualified name: vac:qa:nomos:2025q1-da-testing:networking-privacy
  • owner: romanzac
  • status: done
  • start-date: 2025/01/20
  • end-date: 2025/02/21

Description

Add integration tests focusing on the privacy of the data in transit

Deliverables

Denial of Service (DoS) and Robustness Testing

  • fully qualified name: vac:qa:nomos:2025q1-da-testing:dos-robustness
  • owner: romanzac
  • status: done
  • start-date: 2025/02/24
  • end-date: 2025/03/21

Description

Add integration tests to verify systems resilience to DoS attacks and handling of large volume of data

Deliverables

Edge Cases

  • fully qualified name: vac:qa:nomos:2025q1-da-testing:edge-cases
  • owner: romanzac
  • status: done
  • start-date: 2025/03/24
  • end-date: 2025/03/31

Description

This is an ongoing task. Add edge case integration tests to cover unusual system behavior.

Deliverables