doc: info on the release cycle
This commit is contained in:
@@ -25,3 +25,99 @@ Priorities:
|
||||
1. consensus
|
||||
2. wasm
|
||||
3. util
|
||||
|
||||
## Release Cycle
|
||||
|
||||
<table>
|
||||
<tr>
|
||||
<th>Phase</th>
|
||||
<th>Description</th>
|
||||
<th>Duration</th>
|
||||
<th>Details</th>
|
||||
<th>Version</th>
|
||||
</tr>
|
||||
<tr>
|
||||
<td>Dcon0</td>
|
||||
<td>Research</td>
|
||||
<td></td>
|
||||
<td>
|
||||
Research new techniques, draft up architecture design documents and modify the specs.
|
||||
|
||||
During this phase the team looks into new experimental techniques and begins to envision
|
||||
how the product will evolve during the next phase of the cycle.
|
||||
</td>
|
||||
<td>pre-alpha</td>
|
||||
</tr>
|
||||
<tr>
|
||||
<td>Dcon1</td>
|
||||
<td>New features and changes</td>
|
||||
<td></td>
|
||||
<td>
|
||||
Add big features and merge branches. Risky changes that are likely to
|
||||
cause bugs or additional work must be done before the end of this phase.
|
||||
|
||||
The first 10 weeks overlap with the Dcon3 & Dcon4 phases of the previous
|
||||
release, and many developers will focus on bug fixing in those first weeks.
|
||||
|
||||
Developers dedicate a steady 1-2 days/week to the bug tracker, focusing on
|
||||
triaging and newly introduced bugs.
|
||||
</td>
|
||||
<td>alpha</td>
|
||||
</tr>
|
||||
<tr>
|
||||
<td>Dcon2</td>
|
||||
<td>Improve and stabilize</td>
|
||||
<td></td>
|
||||
<td>
|
||||
Work to improve, optimize and fix bugs in new and existing features.
|
||||
Only smaller and less risky changes, including small features, should be
|
||||
made in this phase.
|
||||
|
||||
If a new feature is too unstable or incomplete, it will be reverted before the end of this phase.
|
||||
Developers spend 2-3 days/week in the bug tracker, triaging, fixing recently introduced or prioritized module bugs.
|
||||
</td>
|
||||
<td>alpha</td>
|
||||
</tr>
|
||||
<tr>
|
||||
<td>Dcon3</td>
|
||||
<td>Bug fixing only</td>
|
||||
<td>2 months</td>
|
||||
<td>
|
||||
Focus on bug fixing and getting the release ready.
|
||||
|
||||
Development moves to the stable stabilizing branch. In
|
||||
master Dcon1 for the next release starts.
|
||||
stable is regularly merged into master.
|
||||
|
||||
|
||||
High priority bugs dictate how much time developers will spend in the
|
||||
tracker as oppose to work on the next release Dcon1 features.
|
||||
</td>
|
||||
<td>beta</td>
|
||||
</tr>
|
||||
<tr>
|
||||
<td>Dcon4</td>
|
||||
<td>Prepare release</td>
|
||||
<td>2 weeks</td>
|
||||
<td>
|
||||
Stable branch is frozen to prepare for the release. Only critical and carefully reviewed bug fixes allowed.
|
||||
|
||||
Release candidate and release builds are made.
|
||||
Developers spend a short time 5 days/week with an eye in the tracker for any unexpected high priority regression.
|
||||
</td>
|
||||
<td>release candidate</td>
|
||||
</tr>
|
||||
<tr>
|
||||
<td>Dcon5</td>
|
||||
<td>Release</td>
|
||||
<td>1 week</td>
|
||||
<td>
|
||||
Stage where the final builds are packaged for all platforms, last tweaks
|
||||
to the logs, memes, social media, video announcements.
|
||||
|
||||
The final switch is flicked on [dark.fi](https://dark.fi/) for the new
|
||||
release to show up on the Download page.
|
||||
</td>
|
||||
<td>release</td>
|
||||
</tr>
|
||||
</table>
|
||||
|
||||